Approved out of hours works

Go back to web version

Print version

Current out of hours works

View current out of hours works approved by Council

The following works are scheduled to take place outside of approved construction hours.

Council only approves work outside approved construction hours in specific circumstances. Examples include overnight shop fit-outs or where demolition, excavation or erection of structures may be a risk to public safety during daylight hours.

Approved hours of work

The approved hours of work for a specific development site are contained in the Development Consent.

You can view the Development Consent for each site via our application tracker.

Application tracker

Please note, we are not the only authority who can approve out of hours works. There may be additional approved works we are not aware of (for emergencies, water works etc).

Navigating this page

View current works by clicking next below or clicking the links in the box at the top of the page.

Works by other authorities

Third parties, such as utility companies and state departments, do not have to notify Council of emergency works.

For more details on out of hours works being carried out in your area, check with the following organisations:

Denison Street, North Sydney

Works: Repainting façade using EWP

Work dates: Works will take place over a period of 10 nights, between the hours of 7pm to 3am, weather permitting. Work dates include:

  • Wednesday 8 April to Friday 10 April 
  • Monday 13 April to Wednesday 15 April
  • Friday 17 April 

Contact: Will Townsend, 0413046545

Albany Lane and Oxley Street

Works: Reopen previous works for supply authority outage

Work dates: Works will commence on Friday 17 April for 3 nights, between the hours of 7pm to 5am - weather permitting

Contact: Michael Mirecki, 02 8781 5324

Ben Boyd Road, Neutral Bay

Location:
Ben Boyd Road, from Aubin Street to Kurraba Road, Neutral Bay, NSW 2089.

Works:
Asphalt road restoration works (approximately 1,950 square metres).

Work dates:
Works will take place from Tuesday 7 April 2026 for up to four nights, between 7pm and 5am, Monday to Friday only, weather permitting.
No work will occur on Saturdays, Sundays or Public Holidays.

Contact:
NSW Building and Civil
Project Manager - Nasser
0422 855 552
Admin@NSWBuildingandCivil.com.au

33-35 Atchison Street, St Leonards

Works: Reopen previous works for Supply Authority outage

Work dates: Works will commence on Friday 17 April for 3 nights, between the hours of 7pm to 5am - weather permitting 

Contact: Michael Mirecki, 02 8781 5324

Myrtle Street, Crows Nest

Location:
Myrtle Street at the Pacific Highway, Crows Nest

Works:
Construction of a new raised pedestrian crossing

Work dates:
Works are planned to begin on Tuesday 7 April 2026 and will be completed within two weeks, weather permitting.
Standard working hours will be 7am – 5pm.

Contact:
Civotek Project Manager Rawi Sader on 0450 494 791 or Council Representative Jim Moore on 02 9936 8233 or Jim.moore@northsydney.nsw.gov.au

Telopea Street, Wollstonecraft

Location:
Telopea Street, Wollstonecraft – outside properties 5 to 15

Works:
Road works

Work dates:
Works will take place from Monday 30 March 2026 to Wednesday 1 April 2026, between 7am and 5pm Monday to Friday (and 8am to 2pm Saturday if required), weather permitting.

Contact:
Shamrock Developments International on 0413 671 225. Alternatively, you can contact Council’s Engineering Project Manager, Ashraf Doureihi, on 0421 020 129 or ​ashraf.doureihi@northsydney.nsw.gov.au​.

1 Balls Head Rd, Waverton

Location:
Front of property at 1 Balls Head Road, Waverton

Works:
Night works for State Significant Infrastructure involving float delivery of a long reach excavator. Works will require a large delivery/float truck and will temporarily impact 11 on-street parking spaces and two traffic lanes on Council’s roadway.

Work dates:
Works will take place on Wednesday 8 April 2026, between 9pm and 5am.

Contact:
Acciona Representative Liz Macmillan on 0412 511 636 or liz.macmillan@acciona.com

12 William Street, North Sydney

Location:
12 William Street, North Sydney & outside 40 Mount Street on William Street, North Sydney.

Works:
Asphalt road restoration works (approximately 70 square metres).

Work dates:
Works will take place on Wednesday 08 April 2026, between 7pm and 5am, weather permitting.
Works will occur for one night only.

Contact:
North Sydney Council, 

council@northsydney.nsw.gov.au

(02) 9936 8100

 

195 Ernest Street, Cammeray

Location:
195 Ernest Street, Cammeray NSW 2062

Works:
Asphalt road restoration works (approximately 67 square metres)

Work dates:
Works will take place on Wednesday 8 April 2026, between 7pm and 5am, weather permitting.

Contact:
NSW Building and Civil
Project Manager - Nasser
0422 855 552
Admin@NSWBuildingandCivil.com.au

Ben Boyd Road, Neutral Bay

Works: Asphalt Road Restoration Works

Work dates: Works will commence on Monday 20 April for 1 to 2 night, between the hours of 7pm to 5am  - weather permitting.

Contact: Sam Arbid, 0420 596 496
 

155 Miller Street, North Sydney

Works: Pile excavation for light pole footings

Work dates: Works will commence on Thursday 9 April until Friday 10 April, between the hours of 8pm to 5am, weather permitting.

Contact: Allie Green, 0420277482