Council only approves work outside standard construction hours in extreme circumstances. Examples include overnight shop fit-outs or where demolition or erection of structures may be a risk to public safety during daylight hours. 

Please note, we are not the only authority who can approve out of hours works. There may be additional approved works we are not aware of (for emergencies, water works etc).

Council has a management plan for out of hours works which provides additional guidance.

Standard construction hours

Monday to Friday
7am - 7pm (for B3 Commercial Core and B4 Mixed Use)
7am - 5pm (for all other zones)

Saturday
8am - 1pm

Sunday 
No work permitted

Current out of hours works

Bay Road and Edward Street, Waverton

Works: upgrade of the existing pedestrian crossings

Contact: Rawi Sader, Civotek, 0450494791

Work dates: Works will commence on Monday 6 January and will be completed within 4 weeks, weather permitting. Working hours will be between 7am to 5pm. Line marking to be completed between 7pm to 11pm over 1 shift.

Bay Road and Edward Street, Waverton

Works: upgrade of the existing pedestrian crossings

Contact: Rawi Sader, Civotek, 0450494791

Work dates: Works will commence on Monday 6 January and will be completed within 4 weeks, weather permitting. Working hours will be between 7am – 5pm. Line marking to be completed between 7pm -11pm over 1 shift.

Letter to residents

Rodborough Avenue, Crows Nest

Works: Excavation for electrical upgrade works

Contact: Scott Electrical Services, Bindu Kommi, 0475461688

Work dates: Works will commence on Tuesday 14 January to 16 January and Wendesday 22 January to Thursday 23 January, 9pm-5am, weather permitting.

Milson Park, North Sydney

Works: Essential seawall stabilisation works at Milson Park

Contact: Shamrock Developments International Pty Ltd, Michael Reidy, 0413 671 225

Work dates: Monday 20 January, 7am to 6pm Monday to Friday, 8am to 5pm Saturday (occasional night works to suit changing tide levels), 4 weeks duration, weather permitting.

Letter to residents

Location of works

Pacific Highway, North Sydney

Works: Hoarding and mast climber install

Contact: RM Watson, Adam Keelan, 0411989675

Work dates: Saturday 18 and Sunday 19 January, 8am-6pm, weather permitting

 

Works by other authorities

Third parties, such as utility companies and state departments, do not have to notify Council of emergency works.

For more details on out of hours works being carried out in your area, check with the following organisations:

Go back to web version