Print version
When Council or Council's contractor undertakes infrastructure or road works, we must follow standard working hours.
Standard construction hours
Monday to Friday
- 7am - 7pm (for B3 Commercial Core and B4 Mixed Use)
- 7am - 5pm (for all other zones)
Saturday
- 8am - 1pm
Standard demolition and excavation hours
- Monday to Friday only, between 8am and 5pm
Start and end times are estimates only (weather and other factors permitting). All efforts will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.
Council may approve construction works outside of standard hours for public safety reasons.
View current Council or contractor works
View current works by clicking next below or clicking the links in the box at the top of the page.
Willoughby Road, Crows Nest
More information about the Willoughby Road upgrade.
Primrose Park, Cremorne
Works: Upgrade works
Contact: Ali Makouk, EzyPave, 0450 090 759
Work dates: Works will commence on Monday 10 February 2025, 7am to 5pm Monday to Friday, and are scheduled to be completed within 4 weeks (weather and other factors permitting)
Waverton Park, Waverton
Works: stormwater quality improvement works
Contact: Kevin Azzopardi, Azbuild, 0416 121 099
Work dates: Works are scheduled to start on Monday March 10, and be completed within 7 weeks, depending on weather and other factors. Work will take place between 7am and 5pm, Monday to Friday.
Blues Point Reserve
Works: upgrading the pathway lighting
Contact: Ali Herz, TOBCO, 0450506445
Work dates: Tuesday 24 March to Sunday 15 June, 7am to 5pm Monday to Friday, weather permitting.
McMahons Point, North Sydney and St Leonards
Works: Footpath and Road Restoration Works
Contact: Nasser, NSW Building and Civil Pty Ltd, 0422 855 552
Work dates: Works will commence on Monday 31 March, 7am to 5pm Monday to Friday and 8am to 2pm Saturdays, and are scheduled to be completed within 1 to 2 weeks (1 day at each location), weather and other factors permitting
Lavender Bay Jetty
Works: Works will include full replacement of the timber stairs, fenders, and baffles
Contact: Felipe Carvalho, GPM Marine Constructions, 0414 024 350
Work dates: Works will commence on Wednsday 12 March, 7am to 5pm Monday to Friday and 8am to 2pm Saturdays, and are scheduled to be completed within 3 weeks, weather and other factors permitting
Young Street Cycleway
Works: upgrade works will include construction of new cycleway, stormwater drainage, footpath upgrade and a pedestrian/bicycle crossing
Contact: Ali Makouk, EzyPave, 0450 090 759
Work dates: works will commence on Monday 24 March, 7am to 5pm, Monday to Friday and 8am to 2pm Saturdays, and are scheduled to be completed within 6 weeks, weather and other factors permitting
Find out more about the project
Yeo Street and Watson Street, Neutral Bay
Works: Footpath, Kerb & Gutter and Drainage
Contact: Rawi Sader, Civotek, 0450 494 791
Work dates: Works will take place Wednesday 3 April, 7am to 5pm Monday to Friday, and are scheduled to be completed within 2 weeks, weather and other factors permitting.
Watt Park, Lavender Bay
Works: minor maintenance works on the retaining wall
Contact: Shamrock Developments International, 0430 592 240
Work dates: Works will commence on Monday 7 April, 7am to 5pm Monday to Friday and 8am to 2pm Saturdays, and are scheduled to be completed within 3 days, weather and other factors permitting
Mchatton Street & Pacific Highway, North Sydney
Works: reconstruct a Continuous Footpath Treatment
Contact: Rawi Sader, Civotek Project Manager, 0450 494 791
Work dates: Works will commence on Monday 14 April, 7am to 5pm Monday to Friday and 8am to 2pm Saturdays, and are scheduled to be completed within 2 weeks, weather and other factors permitting
Bydown Street, Neutral bay
Works: reconstruction of concrete kerb and gutter (K&G), layback, footpath, and driveways
Contact: Nader, 0410 421 999
Work dates: Works will take commence Saturday 12 April, 7am to 5pm Monday to Friday and 8am to 2pm on Saturdays, and are scheduled to be completed within 1 - 2 weeks, weather and other factors permitting.