Council road and infrastructure works

Go back to web version

Print version

When Council or Council's contractor undertakes infrastructure or road works, we must follow standard working hours.

Standard construction hours

  • Monday to Friday - 7am to 5pm
  • Saturday - 8am to 1pm
  • Sunday and Public Holidays - no work is permitted

Standard demolition and excavation hours

  • Monday to Friday only, between 8am and 5pm

Start and end times are estimates only (weather and other factors permitting). All efforts will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

Council has a management plan for Out of Hours works which provides additional guidance.

View current Council or contractor works

View current works by clicking next below or clicking the links in the box at the top of the page.

Willoughby Road, Crows Nest

Works: underground the overhead power cables

Contact: Garde Services, 02 9737 9062

Work dates: Works will commence in October 2023 and finish in May 2024, weather permitting.

Letter to residents

 

Works: stormwater drainage construction

Contact: Edmond Nouneh, Ally Civil, 0416 538 083

Work dates: Works will commence on Monday 11 March and will finish in June 2024, weather permitting.

Letter to residents

 

Works: footpath paving works

Contact: Edmond Nouneh, Ally Civil, 0416 538 083

Work dates: Works will commence on Monday 6 May and will finish in June 2024, weather permitting.

Letter to resident and business owners

 

More information about the Willoughby Road upgrade.

Crows Nest Road, Waverton

Works: Upgrade works at the intersection of Crows Nest Road and Carr Street, Waverton, including kerb and gutter extensions, reconstruction of kerb ramps and footpaths, modification of drainage pit lids, and construction of a new roundabout and traffic islands.

Contact: Mohammad Karim, EzyPave, 0410 828 975

Work dates: Works will commence 2 April and be completed within six weeks, weather permitting. A site compound will be established from 25 March, occupying up to three parking spots.

Letter to residents

Honda Road, Cremorne Point

Works: stormwater improvement works

Contact: Kevin Azzopardi, Azbuild, 0416 121 099

Work dates: Works will commence Monday 8 April and be completed within eight weeks, weather permitting.

Letter to residents

Grafton Street, Neutral Bay

Works: reconstruction of footpaths

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will commence Tuesday 14 May, 7am to 5pm weekdays and Saturdays 8am to 2pm, and be completed within two weeks, weather permitting.

Letter to residents

Hazelbank Road and King Street, Wollstonecraft

Works: reconstruction of edestrian Refuge islands and new kerb blisters

Contact: Rawi Sader, 0450 494 791

Work dates: Works will commence Monday 20 May, 7am to 5pm weekdays, and be completed within three weeks, weather permitting.

Letter to residents

Spains Wharf Road, Neutral Bay

Works: threshold replacement stair repairs

Contact: Anthony Anzellotti, 0418 223 302

Work dates: Works will commence Wednesday 12 June and be completed within four days, weather permitting.

Letter to residents

Hazelbank Road, Wollstonecraft

Works: reconstruct drainage and kerb and gutter

Contact: Rawi Sader 0450 494 791

Work dates: Works will commence Monday 3 June, 7am to 5pm and be completed in three weeks, weather permitting.

Letter to residents

Mount Street, North Sydney

Works: road and footpath restoration

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will commence Saturday 8 and 22 June, 8am to 5pm, weather permitting.

Letter to residents

Little Spring Street, North Sydney

Works: road and footpath restoration

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will continue Saturday 22 June, 8am to 5pm, weather permitting.

Letter to residents

Cowdroy Avenue, Cammeray

Works: replace the timber fence

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will commence Monday 17 June, 8am to 5pm, for five days weather permitting.

Letter to residents

Wyagdon Street and Bent Street, Neutral Bay

Works: upgrading stormwater drainage, kerb and gutter reconstruction, footpath reconstruction, stone block walls, construction of new concrete stairs and new stair lighting

Contact: Moe Karim from EzyPave, 0410 828 975

Work dates: Works will commence Monday 17 June, to be completed in 10 weeks, weather permitting.

Letter to residents

Carter Street, Cammeray

Works: Upgrade Footpath/Driveway, Kerb & Gutter

Contact: Civotek Project Manager Rawi Sader,  0450 494 791

Work dates: Works will commence on 8 July, and will be completed within 2 weeks, weather permitting.

Letter to residents

Go back to web version