Council road and infrastructure works

Go back to web version

Print version

When Council or Council's contractor undertakes infrastructure or road works, we must follow standard working hours.

Standard construction hours

  • Monday to Friday - 7am to 5pm
  • Saturday - 8am to 1pm
  • Sunday and Public Holidays - no work is permitted

Standard demolition and excavation hours

  • Monday to Friday only, between 8am and 5pm

Start and end times are estimates only (weather and other factors permitting). All efforts will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

Council has a management plan for Out of Hours works which provides additional guidance.

View current Council or contractor works

View current works by clicking next below or clicking the links in the box at the top of the page.

Willoughby Road, Crows Nest

More information about the Willoughby Road upgrade.

Woolcott Street, Waverton

Works: Upgrade works of Merrett Playground

Contact: Civilscape Pty Ltd, 0403 219 971

Work dates: Works will commence on Thursday 25 July, and is expected to be completed within 12 weeks, weather permitting.

Letter to Residents

Colin Street, Cammeray

Works: Kerb & gutter, footpath, driveway, and minor drainage works

Contact: Anzellotti Constructions, 0418 223 302

Date and times: Works will commence on Tuesday 20 August and will take approximately three weeks to complete, weather permitting. Work hours will be 7am to 5pm Monday to Friday, and 8am to 1pm on Saturday.

Letter to residents

McLaren Street, North Sydney

Works: Crane works

Contact: Tony Mitevski, Buildgroup Aus Services, 0414302020 

Work dates: Works will commence on Saturday 12 October, 7am-5pm, weather permitting

Bellevue Street, Cammeray

Works: Reconstruction of Refuge Islands

Contact: Rawi Sader, Civotek , 0450 494 791

Work dates: Works will commence on Monday 30 September, and will be completed within 2 weeks, weather permitting. Working hours will be between 7am – 5pm. Line marking to be completed between 7pm -10pm.

Letter to residents

Kurraba Road, Neutral Bay

Works: Stabilisation works

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will commence on Tuesday 8 October to Monday 14 October, within the hours of 7am-5pm, weather permitting. 

Letter to residents

Bray Street, North Sydney

Works: Retaining wall works, removal of vegetation

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will take place from Thursday 3 October until Saturday 5 October, Monday -Friday 7am-5pm, Saturday 8am-1pm, Weather Permitting

Letter to residents

Balls Head Drive, Waverton

Works: Construction of new stairway

Contact: Mohammad Karim, EzyPave, 0410 828 975

Work dates: Works will commence on Thursday 10 October to Thursday 24 October, Monday-Friday 7am-5pm, Saturday 8am-1pm weather permitting.

Letter to residents 

Lodge Road Playground, Cremorne

Works: removal of selected existing equipment, the installation of new play structures, the addition of edging, sandstone boulders, and other natural elements, as well as the installation of organic and rubber safety surfacing and new park furniture

Contact: Civilscape Pty Ltd, 0403 219 971

Work dates: Works will commence on Monday 14 October and are expected to be completed within 8 weeks, weather and other factors permitting.

Letter to residents

Balls Head Peninsula, Waverton

Works: Drainage, Retaining wall & Civil Infrastructure Works

Contact: Rawi Sader, Civotek Project Manager, 0450 494 791

Work dates: Works will commence on Monday 28 October, and are expected to be completed within 6 weeks, weather permitting. Working hours will be Monday to Friday 7am to 5pm, and Saturday 8am to 1pm.

Letter to residents

Spruson Street, Neutral Bay

Works: Drainage works

Contact: Rawi Sader, Civotek Project Manager, 0450 494 791

Work dates: Works will commence on Monday 11 November, and is expected to be completed within 2 weeks, weather permitting. Working hours will be between 7am – 5pm.

Letter to residents

Forsyth Park, Neutral Bay

Works: Drainage works

Contact: Rawi SaderCivotek Project Manager, 0450 494 791

Work dates: Works will commence on Monday 11 November, and are expected to be completed within 2 weeks, weather permitting. Working hours will be between 7am – 5pm.

Letter to residents

Little Spring Street, North Sydney

Works: Road works (final stage of the laneway upgrade)

Contact: Shamrock Developments International, 0430 592 240

Work dates: Works will take place on Saturday 9 November, Saturday 16 November and Sunday 17 November, and are expected to be completed within 12 weeks, weather permitting.  Working Hours 7am-5pm .

Letters to residents

Go back to web version