Works Zone Permit Application - New

We recommend to have all the required documents ready before commencing as the form will time out after 30 minutes and the form progress cannot be saved. 

NB: The minimum duration for the works zone application is 16 weeks.

You will need to provide the following documents in this form:

  • Construction Traffic Management Plan (CTMP) approval letter
  • If a CTMP is not required, please provide the following (if required):
    • Swept Paths for truck movements
    • truck sizes
    • Traffic Guidance Scheme (TGS)
  • Copy of your currencies and insurances with a minimum of $20,000,000 public liability, noting North Sydney Council as an interested party
  • Tree management plan approval letter from Planner or Tree Management team, if required
  • A small map extract of where the works zone will be located (Refer to example of how to create a locality sketch)
  • Completed security deposit form (Click here to dowload and please fill in the required field before uploading)

    Please ensure information provided in the form & as attachments is accurate, as incorrect information will incur delays in progressing your application.

    We only accept documents in the following formats: document (.doc, .docx, .pdf), text (.txt, .rtf) & image (.jpg, .bmp, .png, .gif) and maximum total size of attachments is 35MB