North Sydney Olympic Pool redevelopment

Timeline of works

2024 November

Progress this month includes the commencement of zinc cladding installation on Level 4, further enhancing the facility's design. High-level services have been completed on Level 3, as well as in the new Level 2 gym area. Tiling of the walls adjacent to the 50m pool is now underway, with internal waterproofing and wall tiling continuing on Level 1.

A significant milestone was achieved with the recent commissioning of the electricity substation, providing permanent power to the site and supporting ongoing construction and future operations.

Please see the latest edition of our North Sydney Olympic Pool monthly e-newsletter for all the latest information.

Read e-news edition 4

 

2024 October

The Southern Wall heritage restoration is now complete, marking a major milestone in preserving the site's historic character. The high-level services installation in the gym has also been completed, and the structural steel installation for the 25m pool upper roof is nearing completion.

Work continues on the outdoor leisure pool with preparatory works now underway, and the seawater intake system is successfully connected to the seawall and wharf, supporting sustainable water use for the pools. The mechanical plant installation is progressing steadily, and the services and ceiling finishes in the Eastern Stair Tower are nearing completion as well.

Please see the latest edition of our North Sydney Olympic Pool monthly e-newsletter for all the latest information.

Read e-news edition 3

2024 September

The Western Stairs' heritage wall restoration is now complete. The Southern Wall heritage restoration, and construction of the changing rooms, gym and internal spaces are progressing steadily, with the enclosure works continuing. The construction of the sundeck on Level 2 is also nearing completion and the structural steel for the 25m pool hall is being installed.

The gym space continues to take shape, with the installation of all mechanical, hydraulic and electrical services - and the wall linings encasing these services – now complete. The southern side glazing is nearing completion, and the ceiling finishes are also underway.

Please see the latest edition of our North Sydney Olympic Pool monthly e-newsletter for all the latest information.

Read e-news edition 2

2024 August

Construction across the site is continuing and tiling of the outdoor 50m pool is now complete.

The western tower heritage restoration works are also now complete and the fit-out of plant rooms on levels 1 and 2 is progressing.  

High-level services on level 3 have begun to be installed, and internal walls and ceilings are being 'closed in'. 

Please see the first edition of our North Sydney Olympic Pool monthly e-newsletter for all the latest information.

Read e-news edition 1

2024 April

Commencement of the 50m floor tiling

2023 December

The wall tiling of the 50m pool completed and commencement of the sundeck construction

2023 August

Council resolved to appoint external project management specialists APP Group 

2023 April

Independent review of the North Sydney Olympic Pool redevelopment project was commissioned and reported to Council

2021 March

Work begins on site

2020 December

Icon SI (Aust) Pty Ltd appointed to redevelop the North Sydney Olympic Pool.

2020 October

Final detailed design and tender documentation completed. Tenders called from a short list of eight prospective tenderers derived from an earlier Expression of Interest process.

2020 July

North Sydney Olympic Pool redevelopment received approval from the Sydney North Planning Panel on 1 July 2020. 

2020 April

Council resolves to adopt amended plans. View amended DA plans and other documentation through DA Tracking (search for DA 347/19 in the search field).

2020 March

Brewster Hjorth Architects informs Council that the independent planner assessing the application has requested further information and design changes to address predominantly heritage issues.

2019 October

DA lodged and placed on public exhibition.

2019 August

Progress is reported to Council and DA phase of the redevelopment project begins.

2019 March

North Sydney Council votes to progress redevelopment to Stage 2 Design – Preparation of a DA and Statutory Approvals. For more information on the redevelopment view Report to Council 25 March 2019Media Release 26 March 2019.

2018 June

Following an extensive Tender process for Design and Project Management Services, Brewster Hjorth Architects and sub consultant team are appointed to redevelop the NSOP complex.

2017 November

A mayoral minute was put to Council where it was resolved to continue the project with Option 2.

2016 March

Outcome of Phase 2 Community Consultation reported to Council. Council resolves to defer the project. View NSOP Redevelopment Options March 2016Addendum NSOP Community Consultation Results March 2016.

2015 August

Phase 2 Community Consultation of six options conducted.

2015 March

Council resolves to present six options developed from Phase 1 Community Consultation.

2014 December

Consultation findings presented to Council.

2014 September to November

Phase 1 Community Consultation conducted.

2014 December

Redevelopment masterplan options prepared by consultants.

2013 July

Redevelopment of North Sydney Olympic Pool approved by Council.

pool enews header

North Sydney Olympic Pool updates

We've launched a monthly e-newsletter to keep you informed on the redevelopment progress.

Sign up